Cyprus 5% VAT on a Primary Residence: The 15 June 2026 Deadline Many Buyers Are About to Miss
A transitional window that has let thousands of buyers in Cyprus pay just 5% VAT on a main home is closing. For a large group of purchasers and self-builders, the last day to lodge the claim is 15 June 2026. A separate amending law passed in April 2026 has given some applicants until 31 December 2026 — but not everyone qualifies, and the difference between the two dates can be worth tens of thousands of euro.
Table of Contents
- The 5% reduced VAT rate, in brief
- The transitional regime: who Article 63 covers
- Two deadlines: 15 June 2026 or 31 December 2026
- Why the building permit date decides which one applies
- What a “duly completed” declaration needs
- Keeping the 5%: the ten-year condition
- What to do now
- Frequently asked questions
This guide explains who is on which deadline, why the date of the building permit — not the planning permission — decides the question, and the practical steps to secure the reduced rate before the window shuts. It is general information on Cyprus VAT, not advice on a specific purchase.
The 5% reduced VAT rate, in brief
Cyprus applies a reduced VAT rate of 5% — instead of the standard 19% — on the acquisition or construction of a dwelling used as the buyer’s principal and permanent residence in the Republic. The relief is generous but capped. Under the current regime it covers the first 130 square metres of buildable area, for a value of up to €350,000, provided the total transaction value does not exceed €475,000 and the total buildable area does not exceed 190 square metres.
More generous limits apply to particular groups. A person with a disability receives the 5% rate on the first 190 square metres irrespective of the home’s total area, and large families gain an extra 15 square metres of allowance for each child beyond three. Above the value or area ceilings, the standard 19% rate applies to the whole price. Buyers weighing a new build should read this alongside our guide to buying off-plan property in Cyprus.
The transitional regime: who Article 63 covers
The 130-square-metre regime arrived with the VAT (Amending) Law of June 2023, adopted after pressure from the European Commission. To protect buyers already in the pipeline, the same law added a transitional provision — Article 63 of the VAT Law — preserving the older, looser regime, which applied the 5% rate to the first 200 square metres of a home regardless of total size.
Article 63 applies to any building for which a planning permission had been obtained, or an application for planning permission had been filed with the competent authority, by 31 October 2023. For those projects, the reduced rate on the first 200 square metres remains available — on condition that the buyer files a “Responsible Declaration” (Yπευθυνη Δηλωση) with the Tax Department within three years of the law’s entry into force on 16 June 2023. Three years takes that window to 15 June 2026.
Two deadlines: 15 June 2026 or 31 December 2026
In April 2026 the legislature passed a further amending law (N.109(I)/2026, published on 24 April 2026). It allows the Tax Commissioner to examine Responsible Declarations filed under Article 63 up to 31 December 2026 where their examination could not be completed in time because of delays by the planning authorities.
A Tax Department announcement of 4 May 2026 set out how the original and extended dates fit together. There are, in effect, two tracks:
- 15 June 2026 — where the planning-permission application was filed by 31 October 2023 and the building permit (αδεια οικοδομησ) was issued by 31 December 2024.
- 31 December 2026 — where the building permit was issued on or after 1 January 2025, or has not yet been issued at all.
Both tracks still require the claim to be made through the Tax Department’s Tax For All (TFA) portal, and both still require entry into the regime through a pre-31 October 2023 planning application.
Why the building permit date decides which one applies
This is the point most often misread. The building-permit date is not, in fact, a criterion in the legislation. Article 63 keys eligibility to the planning permission and fixes a single deadline — three years from 16 June 2023 — for the whole transitional category. The April 2026 law speaks only of examination delayed by the planning authorities, and says nothing about permit dates.
The building-permit date appears in one place only: the Tax Department’s administrative announcement. It is the Department’s practical test for who counts as having been held up by the planning authorities, and therefore who earns the discretionary extension. The logic is simple — if the building permit issued only after 1 January 2025 (or still has not issued), that evidences delay, so the extra time is allowed; if it issued by 31 December 2024, the applicant had ample runway and stays on the ordinary 15 June 2026 deadline.
It follows that a buyer whose permit issued by the end of 2024 is not disadvantaged by the rule — 15 June 2026 was always the statutory deadline. A late or pending permit is simply the only route to more time, and an early permit means that route is closed.
What a “duly completed” declaration needs
The Tax Department will not examine a declaration it does not regard as duly completed, so the supporting file matters as much as the deadline. For a purchase, the declaration is normally lodged before the buyer takes possession of the home, with a proviso allowing submission within twelve months of possession where the delay is justified.
The core attachments for a purchase are:
- the contract of sale;
- the architectural plans (elevations, a 1/100 site plan and an area calculation);
- a certified true copy of the planning-permission application as received by the competent authority; and
- evidence the home is used as the main residence — utility and municipal-tax bills — which may follow within twelve months of taking possession.
A married applicant must file, at the same time, a declaration by the spouse that the spouse owns no other principal residence in the Republic. The applicant must also be at least 18, must hold no other residence in Cyprus acquired with reduced VAT, and must have repaid any government special housing grant previously received.
Keeping the 5%: the ten-year condition
The reduced rate is conditional, not final. If the owner stops using the property as a principal and permanent residence within ten years, the law requires notice to the Commissioner within thirty days and repayment of the difference between the 5% and 19% figures for the unused part of the ten-year period. The Tax Department has been actively pursuing recovery from people who claimed the relief but did not occupy the home, including in the context of the former Cyprus Investment Programme.
Planning a move, a rental, or a transfer within the decade therefore needs advice before it happens, not after. There are limited carve-outs — for example, transfers to an adult child who is themselves a qualifying beneficiary, and death of the beneficiary. For the wider tax picture on a Cyprus move, see our overview of Cyprus tax incentives in 2026.
What to do now
For anyone whose planning application predates 1 November 2023 and whose building permit issued by the end of 2024, the message is urgent: the claim must reach the Tax Department through TFA by 15 June 2026. Three steps make the difference:
- Confirm your track. Check the issue date of the building permit (not the planning permission). On or before 31 December 2024 means the 15 June 2026 deadline; 2025 or later means the December 2026 longstop may be available.
- Assemble the file. Gather the contract, plans, the stamped planning-permission application and proof of residence, plus a spouse declaration where relevant — a declaration missing its attachments will not be examined.
- File on Tax For All. Submit the duly completed Responsible Declaration through the TFA portal and keep the confirmation. Where a deadline is close, do not leave it to the final day.
Used correctly, the relief turns a 19% charge into 5% — on a €340,000 home, a difference of roughly €47,000. Missing the window can mean losing it altogether.
Frequently asked questions
Does the 15 June 2026 deadline apply to me?
If your planning-permission application was filed by 31 October 2023 and the building permit was issued by 31 December 2024, yes — your Responsible Declaration must be on Tax For All by 15 June 2026. If the building permit issued in 2025 or later, you may have until 31 December 2026.
Is the building permit the same as the planning permission?
No. They are separate consents. Eligibility for the transitional 5% rate depends on the planning-permission application date (by 31 October 2023), but which deadline applies — June or December 2026 — depends on the building-permit issue date.
What happens if I miss the deadline?
The transitional benefit lapses and the purchase is exposed to VAT at the standard 19% rate. Because eligibility runs through a pre-31 October 2023 application, missing the window can mean losing the reduced rate rather than simply moving to a different one.
How do I actually file the claim?
The Responsible Declaration is submitted, duly completed and with its attachments, only through the Tax Department’s Tax For All (TFA) system. A declaration treated as incomplete will not be examined.
Can I lose the 5% after I have claimed it?
Yes. If you stop using the home as your principal and permanent residence within ten years, you must notify the Commissioner within thirty days and repay the VAT difference for the unused part of the period, subject to limited exceptions.
Speak to Connor Legal
VAT on Cyprus property is unforgiving on timing and detail, and the June 2026 window leaves little room for error. Connor Legal advises buyers, developers and self-builders on securing — and keeping — the reduced rate. If you are unsure which deadline applies to your purchase, get in touch with our team for a prompt, practical assessment.